Find It  Search our site  
department of public works

Public Works Special Projects

conceptual drawing of the Project One development
Project One

Contractor:
Brasfield and Gorrie
Jeremy Thompson
1990 Vaughn Road Northwest, Suite 100
Kennesaw GA 30144
678-581-6347

Project One is located on the corner of West Washington and Main Street in downtown Greenville. The mixed use development will include the headquarters of Certus Bank, Haynsworth Sinkler Boyd Law Firm and Anthropologie, a women’s apparel and home furnishings retail store. The first phase of construction is a nine-story building, Second phase will be an 11-story building, with 40,000-50,000 square feet of retail store space on the ground floor of the entire complex. As with any downtown construction, juggling schedules and spaces is often challenging. Please be aware that some sidewalks or traffic lanes are closed from time to time. Please follow all directional signs around the construction area. Please note that some concrete pours will be made during the early morning hours. Elevated noise levels are expected. Below is a concrete pour schedule for the facility which will be updated on a regular basis, this is subject to change based on productivity, weather, and/or complications.

Concrete Pour Schedule

Location Level   Start Date Date Complete
NORTH TOWER
  Level 2 Pour A, B, C ---- 2/03/12
SOUTH TOWER
  Level 2 Pour A 2/13/12 Completed
    Pours B and C 2/23/12 Completed
NORTH TOWER
  Level 3 Pour A 3/02/12 Completed
    Pour B 3/07/12 Completed
  Level 4 Pour A 3/15/12 Completed
    Pour B 3/20/12 Completed
  Level 5 Pour A 4/02/12 Completed
    Pour B 4/04/12 Completed
    Pour C 4/09/12 Completed
  Level 6 Pour A 4/18/12 Completed
    Pour B 4/25/12 Completed
NORTH TOWER
  Level 7 Pour A 5/01/12 Completed
    Pour B 5/03/12 Completed
  Level 8 Pour A 5/12/12  
    Pour B 5/15/12  
  Level 9 Pour A 5/22/12  
    Pour B 5/29/12  
  Roof Pour A 6/05/12  
  Pour B 6/08/12  
Green Avenue Phase IIB

Green Avenue intersection view Construction of the City of Greenville’s Green Avenue Phase IIB Project, which began in September 2010, is now complete. Phase IIA was completed in 2004 and included the addition of curb, gutter, sidewalk and storm drainage improvements to Cleo Street, Jenkins Street, a portion of Lincoln Street and McLeod Street. After more than ten years of land acquisition, designing and planning, the residents of the Green Avenue Neighborhood Association are observing this project becoming a reality. As part of the improvements, 18-inch curb and gutter, two foot curb lawns, five foot sidewalks and storm drainage improvements are to be placed along Lafayette Street from Anderson Street to Lincoln Street, Casey Street from Nelson Street to Jenkins Street and Green Avenue at the Intersection of Lincoln and Lafayette Streets intersection of Green Avenue, McLeod Street and Nelson Street. Anderson Street (from the existing two lanes to the city limit line) is also being narrowed from four lanes to two lanes with planted medians as well as curb lawns approximately ten feet in width. One final feature of construction is the implementation of three detention basins. The detention basins will serve as the focal point of a new walking trail being constructed, but they will also serve to reduce storm water runoff flowing downstream from the 25 acre project site.
View Project Map

The project cost approximately $1.2M and was completed ahead of schedule.

Another Community Improvement Logo
Henderson Basin Improvement Project

The Henderson Basin project involves replacing undersized culverts (pipes that are used to convey water) at six roadways within Henderson Basin. The six locations to be upgraded are located at Halidon Road, Parkins Mill Road, Cleveland Street Extension, Wembley Road and two on Henderson Road.

There are three prevailing reasons to upsize the existing culverts. First, the improvements will prevent water from the creek from overtopping the road during most rain events. Currently all six roadways overtop during the 25-year storm event which has a 4 percent chance of occurring any given year. The average depth of water on top of the road at the culvert during a 25-year storm event is two feet which makes the road unsafe for traveling. Second, there are homes that are currently in the 100-year floodplain that are required to pay annually for flood insurance. With these improvements the floodplain will be decreased in areas and some homes will be removed from the 100-year floodplain therefore flood insurance would no longer be required. Finally, there are homes located along the creek that currently flood. Having a home flood is a horrible event for any homeowner to experience. These improvements will prevent many homes from being damaged due to flood waters.

Construction of the first two culvert improvements (Halidon Road and Parkins Mill Road) began in March of 2010. Each crossing will take approximately three months to construct. The remaining four crossing are currently under design and will commence construction in early 2011. As each culvert is constructed, it will require that the corresponding roadway be fully closed within the construction limits, approximately 150 linear feet on each side of the culvert. Traffic will need to be detoured during this time which may cause residents to have a longer commute than normal. This is understandably an inconvenience but, the long term benefits far outweigh the short term inconvenience. Rain events which cause flooding have no schedule, they occur rapidly and many times without warning. Roadways are shut down due to these rain events and homes are flooded. With the improvements the six roadways should no longer flood during the 25-year storm event and all but one should not flood during the 100-year storm event. These improvements should allow homeowners to safely access improved roadways during rain events and reduce residential flooding.

You can follow this project's progress online - visit www.HendersonBasin.com

Contact

Public Works Offices:
360 S. Hudson Street Greenville, SC 29601
Cynthia Wright: (864) 467-4348

Email

Feedback

Click to Take the SurveyHave we recently completed work in your neighborhood? Tell us how we did by filling out this 5-question survey. Take survey.

Project Photo Gallery

Interested in photos of recent city projects? View the Photo Gallery.