Community Center Upgrades

Project Summary

  • Controlled entry doors will be added to all community centers
  • West Greenville Community Center gym will receive a protective floor cover, wall pads, floor scrubber, bleachers and electronic adjusters for the goals - equipment has been ordered and will be installed by February 2019.
  • Nicholtown Community Center will have its entrance redesigned, and bathroom renovated after ADA is addressed at the location.

Status: 

West Greenville Community Center has a new protective floor cover, wall pads, and floor scrubber. In addition, the bleachers have been replaced and the gym was painted.

The controlled entry doors are being installed now.

Nicholtown Community Center's entrance will be redesigned and it's restroom renovated after completion of a Park-wide ADA transition plan.